The exciting project is beginning to take shape, with all excavation works now having been completed.
Here's an overview of the work that is currently taking place:
• Southern Stand and Plaza Piling has been completed
• The first pour of Southern stand level one suspended slab (September)
• East Stand Soil excavation completed
• East Stand piling 95% completed
• Sub structure and foundations have commenced with first retaining wall panels to installed from 3rd September 2012
• Lighting Towers have been re-erected and are in operation
Timeline on works at Adelaide Oval:
March - September 2012: Northern mound and ancillary works
March 2012 - October 2013: Southern Stand and Southern Plaza
March 2012 - March 2014: East Stand
March 2012 - March 2014: Indoor Centre
March 2013 - October 2013: Main Oval Works
March 2014: Project Completion